Missing or torn edge insulation strips
The screed must be able to expand. If the edge strip is missing, the surface cracks and transmits sound directly into the walls.
The heating pipes will be permanently covered by the screed. Check and photograph pipe routing, edge insulation strips and critical transitions now. Undetected damage later causes cold areas, leaks or complex repairs.
The screed must be able to expand. If the edge strip is missing, the surface cracks and transmits sound directly into the walls.
A crushed heating pipe permanently reduces the flow. The room behind it will never get properly warm.
Where heating loops cross a joint, they need a protective sleeve. Otherwise, the movement of the screed rubs the pipe open.
Spacing that is too wide leads to cold strips in the floor; too narrow leads to unnecessary material use and control problems.
The pipes must be under pressure during the pouring. Only then is damage noticed immediately – otherwise the leak is only searched for in the finished floor.
Photograph every room in its entirety. This documents the spacing of the heating loops for later checks.
Take close-ups of pipes at doors and crossing points. Make sure that pipes are not crushed and protective sleeves are in place at joints.
Walk through every room and record whether the edge insulation strip is sitting continuously all around.
Photograph the open manifold cabinet including labelling. Make sure that the pressure gauge is clearly legible.
Upload your photos and have edge strips, pipe routing and manifold checked for visible abnormalities before the screed comes.