Support frames fixed too weakly
A wall-hung WC must carry substantial loads. If the frames are not correctly connected to floor and wall, the whole prewall works loose.
Fixings, connections and installation heights are still visible now. After boarding, only a small access remains. Therefore, photograph the entire assembly and all details today.
A wall-hung WC must carry substantial loads. If the frames are not correctly connected to floor and wall, the whole prewall works loose.
If the heights for basin, WC or shower are incorrect, the ordered ceramics will not fit later or will sit visibly crooked.
Without decoupling, every flush is transmitted to the adjacent room. This is practically impossible to fix in the finished bathroom.
Every connection behind the boarding must be tested and recorded before closing up.
Photograph the open prewall completely so that all connections are in the picture.
Take close-up photos of the screw connections on all support feet as well as the wall brackets.
Record the height of WC, basin, fittings and drain, each with a visible measuring tool.
Document the type, connection and the later accessibility of the inspection hatch.
Secure the test report of the pipes. Additionally, photograph the acoustic decoupling on the frame and pipes.
Upload your photos and receive a structured evaluation on fixings, heights and connections.